  MRT Report 9-24-2001

     The news is good, and getting better.  The basic story is turning into that the Green/Yellow Lines will open first, hopefully now within a month and the Blue Line after, maybe 3 or more months.  

     Regarding the Green/Yellow lines, the most heavily damaged station was the Main Station.  Speaking with the press office today, the Main Station has been fully drained of water.  Engineers expect a one month repair process.  They are outlining a number of scenarios for getting these lines operational again.  The most popular one is to reconnect the stops, but have the trains bypass the Main Station.  That could get the Green/Yellow Lines back up within a month.  

     The Blue Line is another story.  Long projections, initially as high as six months,  continue and the work goes on.     

 

 